German manufacturer of wind turbines Nordex SE said on Monday that it has gained an order from German green energy company Alterric for Greece.
Nordex said it received the order for nine N175/6.X turbines from Alterric for its 56 megawatt (MW) wind farm in Greece.
The contract also includes service of the turbines for a period of 25 years, Nordex said.
Installation of the turbines with 6.8 MW capacity is expected to begin at the end of 2025, with complete commissioning scheduled for mid 2026, Nordex said.